Summer 2005
Five housing associations selected by the council and Heygate TRA to build new homes on sixteen sites in Elephant and Castle
Spring-Autumn 2006
Architectural competition for each site held. Council, housing associations and tenant representatives consider designs submitted by architects for new homes
Winter 2006
Detailed design work and legal processes agreed
Spring/Summer 2008
Schemes start to be submitted for planning permission
Spring/Summer 2008
First planning permissions received
Winter 2008/2009
Construction of new homes begins
Autumn 2009/Spring 2010
First new homes finished and tenants move in.
![]()